Record review · Seagrove PUD · St. Lucie County, Florida

Lot 4 · 3683 Angler Drive

What the permit files, the recorded plat, the certified surveys and the builder's own warranty portal actually show — every figure traced to its source document. Prepared from the public permit record, the closing survey, and the correspondence file, for review by the builder, counsel and family.

Prepared November 20, 2026 · Elevations in feet, NAVD88 · This review states what the records say and where; it draws no legal or engineering conclusions.
Interactive

The lot, built from the survey

A terrain model of Lot 4 interpolated from the as-built elevations on the HPA final survey (field work November 6, 2024) and the permitted design grades — with the surveyed lot arcs (front 44.93 ft, rear 40.00 ft, radii 1140 / 1015 ft) and the original Blender architectural massing from the recovered Lot 4 Elevation Studio (drone-photo-based; illustrative wall heights and roof detail). Drag to orbit · scroll to zoom · click any marker for its values and source.

Water level

View

Point detail

Click a marker on the model — a yard drain, a corner, the slab — to see its design value, its surveyed value, and the document each came from.

HPA final survey, sheet 2
HPA Surveyors final survey, sheet 2 of 2 — last field work November 6, 2024. Values in parentheses are as-built elevations.
Lot 4 on County as-built sheet PD16
Lot 4 on County as-built sheet PD16, with design and as-built values called out.
Lot cross-section against flood stages
Lot 4 cross-section, rear to front, against the permitted lake stages. Vertical scale exaggerated.
1943 → 2026 · from the air

Aerial & drone evidence

The site from above, before, during and after construction: historic county aerials, the January 2024 excavation image, eight stamped EagleView captures spanning three years, and the owner's own drone flights of 2026. Click any image anywhere on this page to open it full-size.

The site before the lots

The environmental record describes scrub in 1943 and citrus grove from 1969 to 2003. No pond, lake or building appears on or beside the Angler Drive lots in any pre-construction aerial through September 2023.

Historic grove aerial stamped 1952
Citrus-grove aerial, stamped 1952 — grove rows across the future Seagrove site. (Filename dates the print 1950; the photo stamp reads 1952.)
Pre-development aerial with lot and footprint overlay
Pre-development aerial with address labels: the citrus rows still stand where 3683 Angler Drive will be; the future lot outline and house footprint are overlaid.
Recent aerial of the built-out development
The built-out development and its lake system, 2026 — the layout the 2006 plans did not show at Lot 4.

January 10, 2024 — a water-filled excavation at the cul-de-sac

Google Earth historical imagery of January 10, 2024, with the recorded plat lines overlaid: a water-filled excavation straddles the Angler Drive cul-de-sac and the front of Lots 2–4 and 50. The sealed Phase 2 plans of August 3, 2023 show no such feature. Lot 4's house footprint sits within the area that image shows under water.

January 10, 2024 aerial with plat overlay showing water-filled excavation
January 10, 2024 — Google Earth imagery with plat overlay. Dark water fills the excavation across the cul-de-sac bulb and the front of the Angler Drive lots; Tract R-1 (street) and Tract O-2 (2.78 ac, behind the rear lot lines) are labelled. Source: Opening Letter, Image 1; plat geometry per Plat Book 121.

The EagleView record — eight stamped captures, January 2023 to February 2026

Eight EagleView aerial captures obtained through the property report from futurelot.com. Each exhibit carries its capture window as stamped on the image; source filenames and SHA-256 hashes are logged in the evidence record (raw/ archive, EagleView_Aerial_Imagery_Evidence.pdf, 10 pp).

EagleView exhibit 1
Exhibit 1 · Jan 7 – 16, 2023
Capture window as stamped by EagleView — site clearing / early earthwork era.
EagleView exhibit 2
Exhibit 2 · Oct 29 – Dec 18, 2023
Capture window as stamped by EagleView.
EagleView exhibit 3
Exhibit 3 · Dec 18, 2023 – Feb 13, 2024
Capture window as stamped by EagleView.
EagleView exhibit 4
Exhibit 4 · Jan 1 – Feb 1, 2024
Capture window as stamped — brackets January 10, 2024, the date of the water-filled-excavation image above.
EagleView exhibit 5
Exhibit 5 · Jan 3 – 28, 2025
Capture window as stamped by EagleView — first winter after closing.
EagleView exhibit 6
Exhibit 6 · Jan 12 – 28, 2025
Capture window as stamped by EagleView.
EagleView exhibit 7
Exhibit 7 · Dec 24, 2025 – Feb 13, 2026
Capture window as stamped by EagleView.
EagleView exhibit 8
Exhibit 8 · Jan 11 – Feb 20, 2026
Capture window as stamped by EagleView — the most recent capture in the record.

Drone photography — DJI flights, 2026

Owner-flown DJI drone imagery. Originals (10–22 MB) are preserved in the raw/ archive under FINALIZED/Photos and FINALIZED/Permits — flight dates per the DJI filenames: August 4 and October 31 – November 3, 2026.

Angler Drive cul-de-sac from above
Angler Drive and its cul-de-sac from altitude: the lot rows, the street, and the preserve beyond. Inlets D-01/D-02 sit at the cul-de-sac's east side.
Roof of 3683 Angler Drive from overhead
The roof of 3683 Angler Drive from directly overhead — the address numeral visible at the porch roof.
Rear yard and swale corridor at dusk
The rear of Lot 4 at dusk: the fenced rear yard and the swale corridor in Tract O-2 beyond the rear lot line.
Owner-annotated drone frame of the rear yard
Owner-annotated frame: green marks the surveyed points along the rear and side lines; blue traces the rear swale; red marks the yard drains, which sit outside the rear lot line.
Roof and driveway from overhead at dusk
Roof, driveway and garage from overhead — the same flight series.
Verified against the source drawings

Design vs. as-built vs. surveyed

Every elevation at and around Lot 4, from the three documents that measure it. Design values from permitted sheet PD16; County as-builts certified "as surveyed on June 20, 2024"; the HPA final survey dated November 6, 2024.

552 density reports · May 2023 – October 2024

≈2,200 tests — and not one of them on Lot 4

The County package holds 552 density reports — about 2,200 individual compaction tests run by UES / GFA International for Lennar (project 3310.2300152.0000). Every one of them sits in a road, a sidewalk or a utility trench. None is on a building pad. None is on lot fill. And none names the yard-drain run that carries Lot 4's stormwater.

≈2,200
density tests in the package
0
on any building pad or lot fill
0
naming YD-22 through YD-38
331
tests at 97.50–97.99% printed "98, Pass"

None of it touches Lot 4

Every report in the 552-file package covers roads, sidewalks and utility trenches — client Lennar, laboratory UES. No report tests the building pads, the lot fill, or the ground under 3683 Angler Drive. The sealed plans themselves contain no lot-fill, compaction or density standard to test against.

The yard-drain run is untested

No report names YD-22 through YD-38 — the pipe run behind Lots 4–19 that Lot 4's two drains feed. Only the run's last two segments, YD-39 and YD-40 at the Lake 12 outfall, were tested: 14 tests, June 17–18, 2024.

Every row says "Pass"

No failure and no retest is recorded anywhere in the package. Recomputed for the record review, 331 tests fall between 97.50% and 97.99% of the reference density — and print as "98, Pass" against a 98% minimum.

Paperwork up to 533 days late

166 of 236 drainage reports are dated August 30 – October 23, 2024 — some filed up to 533 days after the test date. Sixteen road reports were re-issued November 19–20, 2024 with the same readings and new layer labels — the week before the engineer asked the County to release 29 homes, Lot 4 among them.

A lot-fill record exists — elsewhere

One road report's location map is a plan sheet with a legend "One lift / Two lifts / Three lifts," its marks inside individual lots. The map is cropped at about Lot 8. It suggests a lot-by-lot fill record exists outside the package produced to date.

Ten requests — no answer on existence

The compaction report was requested in writing ten times, November 2–10, 2026. No reply states whether it exists. On November 17, 2026 the CDD's inspector (CWI) told the owner that lot compaction "would need to go to Lennar."

The November 2024 release list redrawn with Lot 4 highlighted
Plate 01 from the record review — the engineer's November 2024 key-map exhibit with the twelve red-cloud markups redrawn and Lot 4 highlighted. The clouds are a release list of 29 homes, not a defect mark; the engineer's own letter lists five items still outstanding, including the remaining lakes and passing drainage lamping results.
The yard-drain run behind Lots 4 to 19
The yard-drain run from YD-22 north-east behind Lots 4 to 19 — the run no density report names. Lot 4's drains, YD-23 and YD-24, sit on the untested segment.

These are patterns in the documents. Their significance is for an independent geotechnical engineer.

1943 → 2026

The record, in order

From citrus grove to certificate of occupancy to Chapter 558 notice — each entry dated and sourced. Click a filter to focus on one thread.

Chapter 558 Notice · November 17, 2026

Seven defects, as noticed

The defects as described in the Notice of Claim served on Lennar Homes, LLC and DRP FL 6, LLC — alongside the independent professional findings that bear on each. These are the claimant's allegations and the cited inspection findings, not adjudicated facts.

Lennar case #07787205 · read November 18, 2026

What the builder's own portal says

Sixteen work orders on the active case. The portal's own fields — status, resolution text, and the last-modified minute — exactly as read. CLOSED ≠ RESOLVED: administrative closure does not establish correction of the underlying condition.

Marked complete or merged — photos of November 17, 2026
Marked complete or merged: portal status beside photographs taken November 17, 2026.
YD-24 with standing water, November 18, 2026
YD-24, rear corner of Lot 4, 12:51 PM, November 18, 2026 — water standing on and around the collar.
YD-24 dry, November 16, 2026
The same drain dry at 5:43 PM on November 16, 2026 — the day before the inspector's pre-rainfall visit.
Still outstanding as of November 20, 2026

Records requested — and the questions that remain

The compaction report was requested in writing ten times between November 2 and November 10, 2026. No reply states whether it exists.

Ten records requested from Lennar

    Seven questions for the engineer, the CDD and SFWMD

      The request log, from the emails themselves

      The full email record

      Correspondence — every message, searchable

      All … messages in the Gmail export where Lennar is a direct party (From, To, Cc or Bcc — raw/FINALIZED/Corespondance, parsed from the original .eml files). Type to filter by date, sender, subject or anything in the body; click a row to read the full message.

      Reference

      The 250 facts

      All 250 numbered facts from 3683 Angler Dr — Top 250 Facts for Legal Team and Len (compiled Nov 2, 2026), in eleven sections. Source tags in brackets; "UNVERIFIED" marks facts not yet confirmed against the source document; section K lists conflicts between sources and missing evidence. Type to filter across all of them.

      Evidence base

      Every document in this review

      The uploaded source files, each indexed in full. Click any card to open the document itself in a viewer — PDFs and text are served read-only from the local source_docs/ folder (copies of the raw/ archive).

      Accuracy statement

      Method, corrections and limits

      How this was checked

        Corrections to earlier statements

          Limits